Kulaina's engineers install and commission the panels we build, from placing and levelling them to terminating cables, testing protection and interlocks and energising them with your team. The same people who designed the panel set it to work on site, and hand over as-built drawings and test records when it is done.
What's included
- Site survey of the panel room, cable routes and earthing
- Placement, levelling and earthing of the panels
- Cable termination and busbar joint torque checks
- Pre-commissioning tests: insulation resistance, secondary injection of protection relays and interlock checks
- Energisation and load trials with your team
- Handover with as-built drawings and test records
Visits and response times
| Typical duration | 1 to 3 days for a typical LT panel |
|---|---|
| Area served | Jaipur and across Rajasthan |
| Handover documents | As-built drawings and test records |
Commissioning is where a panel meets the site. We test every interlock and protection setting with the real loads connected, so the first fault after handover trips the right breaker.
Frequently asked questions
Do you commission panels built by other manufacturers?
Yes, after a pre-commissioning inspection. We check the panel against its drawings and test records before energising it, and flag anything that needs correcting first.
What do you need from us before commissioning?
Completed cable laying, a ready earthing system, the protection settings agreed with your consultant or the electricity board, a shutdown window if the panel connects to a live system and, for HT panels, the Electrical Inspector's approval to energise.
Book a service visit
Send your single-line diagram, BOQ or tender reference. An engineer replies within one working day.